Dam Rehabilitation

Beaverton Dam Reconstruction

Complete Flood Control Structure Rehabilitation including mass concrete demolition, forming and pouring of new concrete structure, fabrication of 3 new flood control tainter gates, reconstruction of one existing tainter gates, fabrication and installation of gate sills and rubplates, and installation of a new gate heating system. Total concrete patch repair 6,500 square foot.

LOCATION
Beaverton, MI

DURATION
Sept. 2009 – Dec. 2009
[back to dams