Project Overview

  • Objective: Enhance dam safety, improve water management, and extend the operational life of the dam.

  • Scope:

    • Tainter Gates Replacement:

      • Tainter gates are critical for controlling water flow and managing flood risks. We Removed, Fabricated New, and Replaced 8 at this site.

      • Replacing 8 gates ensures better structural integrity, improved operational reliability, and compliance with modern safety standards.

    • Platform Replacement:

      • 15 platforms are being updated or replaced.

      • This enhances safety for workers and allows better access for inspections and repairs.

Client Benefits

  • Increased Safety: Updated gates and platforms reduce failure risks and improve dam stability.

  • Environmental Compliance: Modern gates help in better flow management, improving fish passage and downstream ecosystems.

  • Operational Efficiency: New equipment reduces maintenance costs and improves energy production consistency.